Skip to Content or Accessibility Information

City Construction Projects

Are you curious about what construction projects are taking place throughout Prescott? Well, you've come to the right place! Below you will find a list of construction projects that are currently underway as well as those projects that are still pending.

For information on the status of construction projects please call the City of Prescott Public Works Department at 928-777-1130.

Projects in Design Phase

Park Avenue - The Park Avenue road reconstruction project, from Canyon Springs Road to Gurley Street will include water, sewer, and roadway improvements. The project design and specifications are currently being completed.

Design plans have been provided to APS, CenturyLink, and CableOne and approved for construction. The utility relocations began the week of August 12th. Construction of new underground utilities and pole relocations should take 2 months to complete contingent upon soil and weather conditions encountered during construction.

In coming months, during utility relocation work, acquisition of limited but necessary right-of-way for the project will continue. Property appraisals have been completed, meetings will be scheduled with individual property owners as necessary to provide information in this regard and to begin negotiations for the needed right-of-way.

The City will advertise the construction project once the relocation of third-party utilities and acquisition of rights-of-way are completed.

Questions regarding the project should be addressed to the City Project Manager, Tim Sherwood at (928) 777-1130 or email to tim.sherwood@prescott-az.gov

Last updated: Friday, April 4, 2014 at 2:47 PM

PDF Project Update      PDF Traffic Update

The project is to design the upgrade to the existing Prescott Resort Pump Station that feeds Pressure Zone 56 from 740 gallons per minute to 1750 gallons per minute. The project has been proposed based on the City Water Distribution Model calling for a new Zone 56 reservoir to be installed at a higher elevation than the existing Prescott Canyon Reservoir with additional capacity. Per the water model master plan, the new Zone 56 reservoir and upgraded Prescott Resort Pump Station will provide required pressures, residential /commercial fire flows to the entire Zone 56 area, and will enhance pressures to the other surrounding water system zones.

City staff has completed review of the 100% design plans and are awaiting the Arizona Department of Environmental Quality's permit for Approval to Construct, prior to bidding out the project. Construction is anticipated to start in the Summer. Project coordination between the Yavapai Indian Tribe's Prescott Resort and Casino will be required to limit any disruptions to the facility.

Questions regarding the project should be addressed to the City Project Manager, Jeff Low at (928) 777-1130 or email to jeff.low@prescott-az.gov.

Last updated: Wednesday, January 16, 2013 at 2:06 PM

PDF Project Update      traffic update not available

Below are links to the Public Works Capital Improvement Projects lists. If you have any questions, please contact the Capital Program Manager, Timothy Burkeen at (928) 777-1130.

PDF FY2013-2018 Public Works Capital Improvement Projects List

Last updated: Wednesday, June 27, 2012 at 3:02 PM

project update not available      traffic update not available

Robinson Drive Improvements: The project generally consists of reconstructing Robinson Drive from Gurley Street to the city limits south of Newport Drive. The project includes new asphalt pavement and new concrete curbs and gutters. Concrete sidewalk will be installed along one side of Robinson Drive. The project also includes the upgrade of existing water and sewer facilities. This project is currently on hold.

Questions regarding the project should be directed to City Project Manager, George Henderson at 9(28) 777-1130.

Last updated: Monday, October 3, 2011 at 1:50 PM

project update not available      traffic update not available

The Rosser Street Reconstruction Phase IV design project consists of topographic survey of street and appurtenant objects, utilities investigations, and the preparation of plans and specifications to reconstruct Rosser Street with new asphalt concrete pavement and replacement of concrete flatwork when found to be deficient, including water and sewer improvements as needed. Changeable radar signs for traffic calming will be considered with the project.

The project limits are Rosser Street from Campbell Avenue to the easterly boundary of The Meadows at Eagle Ridge Unit III subdivision.

The City is seeking Statements of Qualifications from engineering firms to perform design services for the project. Advertising for Statements of Qualifications SOQ) is scheduled to commence on November 24, 2013. A mandatory pre-proposal meeting was conducted on Thursday, December 5, 2013. SOQ's are due by 2:00 PM on Thursday, December 19, 2013. SOQ's will only be accepted from those firms that attended the mandatory pre-proposal meeting.

Last updated: Friday, April 4, 2014 at 3:43 PM

PDF Project Update      traffic update not available

SR89/Side Road Connector - The project consists of constructing a new roundabout on State Route 89 at a future intersection near the vicinity of the Phippen Museum. The project will be designed to accommodate future traffic for projected growth in the area. Design of the project will span fiscal years 2013 and 2014 with construction scheduled for fiscal year 2015.

Questions regarding the project should be addressed to the City Project Manager, Tim Sherwood at (928) 777-1130 or email to tim.sherwood@prescott-az.gov

Last updated: Friday, February 7, 2014 at 9:33 AM

project update not available      traffic update not available

Yavapai Hills Lower Pump Station - This project will consist of relocating the existing Lower Yavapai Hills pump station that feeds pressure zones east of Prescott Lakes Parkway. The pumps will be upgraded from 300 gallons per minute to 750 gallons per minute to meet existing and future domestic and fire flow demands for this area. This project will include installation of new pumps, associated controls and appurtenances, and an above-ground building enclosure adjacent to York Motors.

Questions regarding the project should be addressed to the City Project Manager, Tim Sherwood at (928) 777-1130 or email to tim.sherwood2prescott-az.gov

Last updated: Friday, February 7, 2014 at 9:34 AM

project update not available      traffic update not available