Are you curious about what construction projects are taking place throughout Prescott? Well, you've come to the right place! Below you will find a list of construction projects that are currently underway as well as those projects that are still pending.
For information on the status of construction projects please call the City of Prescott Engineering Services Department at 928-777-1140.
The Airport Pressure Zone is presently fed from a single 8" line tapped off the 12" transmission main from Chino Valley which is located approximately 5,000 feet to the west. The new South Side Runway Loop project will consist of installing a 12" water main from the existing 12" main in Melville Road around the south end of the airport runway and connect to the existing 10" main on the northwest side of the runway. There is currently only one 8" feed to this system.
The new North Side Runway Loop project will install a 12" water main from the existing Airport Pump Station northward beyond the proposed runway extension and connect to the existing 10" main on the northwest side of the runway. This will be a second feed to enhance the existing supply line to this system and service area.
Last updated: Friday, November 20, 2009 at 1:57 PM
Project Update       
Traffic Update
Campbell Street Paving: The purpose of the project is to construct asphalt pavement on unpaved Campbell Street from Hillside Avenue to Madison Street. The project includes construction of concrete curb and sidewalk along the east side of Campbell Street. This is a federally funded project through the U. S. Department of Housing and Urban Development.
Core 5, LLC completed the first phase of the project from Hillside Avenue to Home Street on June 24, 2009. The second phase of the paving which extends from Home Street to Vallejo Street was completed by the City Streets Department on August 19, 2009.
Last updated: Friday, October 9, 2009 at 3:08 PM
project update not available      traffic update not available
Demerse Avenue Reconstruction: The purpose of the project is to reconstruct Demerse Avenue from Whetstine Avenue to Montebello Lane. The project includes new asphalt pavement, upgrade of the existing water system, installation of drainage improvements, and installation of pedestrian access improvements.
Spire Engineering, LLC is the contractor. Construction started on June 1, 2009, with installation of the water improvements being the first order of work. Construction of the water improvements is now complete. Storm drain construction is currently underway. Project completion was expected by the end of October, 2009 but completion will be delayed due to unforeseen utility conflicts. An old gas line has been found to be too shallow to allow for street construction. Relocation of the gas line is underway, delaying roadway construction in the area of the conflict. APS is currently relocating utility poles to accommodate the construction of handicap access ramps and street improvements.
Last updated: Friday, November 20, 2009 at 1:57 PM
Project Update       
Traffic Update
Several activities continue on the Lowe's project site. Approximately 35-percent of the existing MSE walls and associated backfill material have been removed/excavated to include the installation of a PVC under drain pipe and the excavation of the keyway for the soil buttress. The structural installation of wing-walls on the existing box culvert is complete.
The subgrade and aggregate base coarse for the River Trail Roadway section realignment have been installed; a temporary 3/4-inch minus structural cap was placed over the roadway section to protect it from vehicular traffic loads and erosion and sediment control until the contractor can place asphaltic concrete over the roadway section. The new 8-inch water line and the new 12-inch sewer line have been installed and have passed the applicable biological and mechanical tests.
Last updated: Thursday, October 22, 2009 at 9:49 AM
project update not available      traffic update not available
FALL 2009
ZONE 39 utility upgrade
With Phase II construction well under way, the City of Prescott continues
work on utility upgrades to aging water mains and sewer lines in the
downtown area. New sewer lines and services have already been
installed from Park Avenue to Vista Drive. The installation of upsized water
mains continues to progress down Country Club Drive from Park Avenue to
Verde Lane, and is expected to be complete by the end of the year.
Phase III is anticipated to begin in spring 2010, and includes replacing the
the two water storage reservoirs on top of Indian Hill with one, new water
storage reservoir.
This project will upgrade the cityâ??s water system Pressure Zone 39. Upgrades
consist of replacing aged and undersized facilities, and are necessary to
meet current and future water demand and increase fire flow capability.
To receive regular project updates, email:
zone39@esmaz.com
For questions or concerns, call our
Project Hotline at 541.7825
Normal work hours are 7:00 a.m. to
5:30 p.m. Monday through Thursday.
Please be aware of reduced speeds,
flagging operations, road closures and
detours throughout the construction
zone as work progresses.
Visit www.prescottroadconstruction.com for additional project information.
Last updated: Friday, November 20, 2009 at 1:46 PM
Project Update       
Traffic Update
Installation of 12-inch water main and services along White Spar Road from Copper Basin Road to South Granite Street will continue next week. This work will require trenching in the roadway and motorists will experience reduced speeds, lane restrictions, and traffic control where the water line is being installed. Please use caution while driving through the work zone.
Crews will also continue to install 20-inch water main and services at the Granite Creek crossing and on West Aubrey Street. Please be aware of the following impacts:
There will be a partial closure of West Aubrey Street at Granite Creek when crews are working. Motorists will experience reduced speeds, detours, and possible flagging operations.
As part of the installation of the 20-inch water main along West Aubrey Street, crews may perform sewer work under South Montezuma Street. Please be aware of the following impacts:
Lanes may be restricted along South Montezuma Street at West Aubrey Street when crews are working. Motorists will experience reduced speeds, narrow lanes, and possible flagging operations.
Construction of the new Pioneer Pump Station will continue off the roadway. Crews will continue construction of the pump station building structures.
Work will continue off the road. However, motorists should remain alert for construction workers and equipment at the intersection of Pioneer Drive and Hassayampa Drive.
Last updated: Friday, November 20, 2009 at 1:46 PM
Project Update       
Traffic Update